SEARCH BY LOCATION / BY TYPE
Project filters
Clear Filters
ProjectCountryDateStatus
Rehabilitation of the Bucharest-Constanta lineRomania2007-2011Completed
Modernization of the Koscierzyna railway corridorPoland2012-2015Completed
Integrated Transport System for Maputo and MatolaMozambique2011-2013Completed
Completion works of the Arcisate-Stabio lineItaly2015 – 2017Completed
Rehabilitation of the Vinkovci-Tovarnik lineCroatia2008-2010Completed
Riyadh Metro Project – Line 3 – Package 2Kingdom of Saudi Arabia2015 – in progressIn progress
Etihad Rail Shah-Habshan-Ruwais ProjectUnited Arab Emirates2012-2015Completed
Cairo-Aswan line track renewalEgypt2011-2016Completed
Florence-Bologna high-speed line Italy2006-2011Completed
Modernization of the Reda-Hel railway linePoland2011 – 2015Completed
Rehabilitation of the Okucani-Novska railway lineCroatia2012 – 2014Completed
Modernization of the Olsztyn-Szczytno-Szymany linePoland2011 – 2013Completed
Revitalization of the Chorzow Batory – Tczew railway linePoland2011 – 2011Completed


Modernization of the Koscierzyna railway corridor


Country
Poland

Area
NORTHERN POLAND

Location
KOSCIERZYNA-GDYNIA

Start - End
2012-2015

Employer

PKP - Polskie Linie Kolejowe S.A. Centrum


PCM/Engineer

KoltechArshad


General contractor

Salcef S.p.A.


Subcontractor

-


Joint Venture

No


Constructor

Salcef S.p.A.


Salcef share

100%


Salcef Project Manager

Valerio Antenucci


Project Description

Salcef renewed and revitalised 78.5 km of single and double-ballasted track on the Koscierzyna railway corridor, in the sector between Koscierzyna and Gdynia stations, including design, overhead line renewal, procurement and dismantling of materials.


Scope of Work
  • Design activities
  • Procurement of all materials
  • Dismantling of the existing track and replacement of the complete superstructure
  • Welding in CWR of the existing jointed rails and ballast replacement
  • Installation of 6 turnouts
  • Renewal of the overhead line
  • Refurbishment of bridges and viaducts
  • Execution of embankments
  • Construction of 13 platforms