SEARCH BY LOCATION / BY TYPE
Project filters
Clear Filters
ProjectCountryDateStatus
Rehabilitation of the Bucharest-Constanta lineRomania2007-2011Completed
Modernization of the Koscierzyna railway corridorPoland2012-2015Completed
Integrated Transport System for Maputo and MatolaMozambique2011-2013Completed
Completion works of the Arcisate-Stabio lineItaly2015 – in progressIn progress
Rehabilitation of the Vinkovci-Tovarnik lineCroatia2008-2010Completed
Riyadh Metro Project – Line 3 – Package 2Kingdom of Saudi Arabia2015 – in progressIn progress
Etihad Rail Shah-Habshan-Ruwais ProjectUnited Arab Emirates2012-2015Completed
Cairo-Aswan line track renewalEgypt2011-2016Completed
Florence-Bologna high-speed line Italy2006-2011Completed
Modernization of the Reda-Hel railway linePoland2011 – 2015Completed
Rehabilitation of the Okucani-Novska railway lineCroatia2012 – 2014Completed
Modernization of the Olsztyn-Szczytno-Szymany linePoland2011 – 2013Completed
Revitalization of the Chorzow Batory – Tczew railway linePoland2011 – 2011Completed


Riyadh Metro Project – Line 3 – Package 2


Country
Kingdom of Saudi Arabia

Area
RIYADH CITY AREA

Location
RIYADH

Start - End
2015 – in progress

Employer

ARRIYADH DEVELOPMENT AUTHORITY


PCM/Engineer

Parsons-Egis-Systra JV


General contractor

CWG Consortium leaded by Salini - impregilo


Subcontractor

SALCEF - RHOMBERG JV


Joint Venture

Yes


Constructor

SALCEF - RHOMBERG JV


Salcef's share

-


Salcef's Project Manager

Antonino Buccieri


Project Description

The project involves the construction of a 45 km long double track line from Al-Madinah Al Munawwarah Road to Rahman Al Awal Road. The track is mostly superelevated, with 4 km of underground line.


Scope of Work
  • Detailed design of mainline track and the east and west depots
  • Procurement of track materials as rails, fastenings, turnouts, casting concrete and buffer stops
  • Construction of 80.7 km of ballastless track on the main line and 8.2 km of ballastless track in the depot
  • Installation of 31 turnouts