ITALY HIGH SPEED TO REVOLUTIONISE MOBILITY IN SOUTHERN ITALY
Country
ITALY
Area
CAMPANIA
Location
FRASSO TELESE – TELESINO
Duration
2019 – ongoing
Employer
RFI S.p.A.
PMC/Engineer
Italferr S.p.A.
General Contractor
Joint Venture partners:
- Impresa Pizzarotti & C. S.p.A.
- Ghella S.p.A.
- Itinera S.p.A.
- Salcef S.p.A.
- EdS Infrastrutture S.p.A.
Subcontractor
–
Joint Venture
Yes
Salcef share
6,81%
Salcef Project Manager
Manuel Fidanza
Project Description
The project involves the final design and construction of the doubling of the Frasso Telesino-Vitulano section – Frasso Telesino-Telese Lot, part of a larger project to build the first high-speed line linking two of the most important cities in Southern Italy.
The route covers about 30 km, 5,721 m of which is through tunnels, and involves demolishing 16 km of track on the pre-existing line.
The Salcef Group will construct the track, electrification and signalling systems, as well as designing and building electromechanical technology systems.
Scope of Work
- Track works
- Railway electrification system
- Signalling systems
- Design and construction of electromechanical technology systems